May 24, 2019

Building B1 – Ceiling installation was started last week. Now 25% complete (pictures below). Building C1 – (Above left) Ongoing interior plastering work. Building D9 – (Above right) Work has re-commenced on this building. Interior plastering work is on-going. Building E12 – Footing started for this middle zone building last week. Building E40-41-F1 – (Upper […]