December 26, 2019

Project in Brief – Construction holiday: As requested by neighboring resorts, construction will be postponed during the holiday period from 25th December 2019 until 5th January 2020. We have been working overtime to make up for this time and to ensure that the project will be completed on schedule. – Mockup unit: The mockup unit […]

November 29, 2019

Project in Brief – Several more buildings are currently in the construction process. The substructure is now complete for all of them (footing and step beams) and the superstructure is ongoing (beams, columns, slab floor, and so on, up to the roofs). – Mock-up room: This will allow the team to achieve the same view […]

October 25, 2019

(25 October 2019, Phuket) With the dry season finally upon us, we are speeding up the construction of the Grand Himalai Oceanfront Residences project. We have increased the manpower at the construction site to take advantage of the weather the best we can. Although we may experience a few showers during the day, we believe […]

August 1, 2019

With the wet season being on and off so far where we have faced magnanimous issues is in the clearing the rock for the road ways, broad walks and steps, which make it possible to get to each block. The rock breaking has been nonstop working from 7:30 – 5:30pm each day except for Sunday’s […]

May 24, 2019

Building B1 – Ceiling installation was started last week. Now 25% complete (pictures below). Building C1 – (Above left) Ongoing interior plastering work. Building D9 – (Above right) Work has re-commenced on this building. Interior plastering work is on-going. Building E12 – Footing started for this middle zone building last week. Building E40-41-F1 – (Upper […]