December 30, 2020
  Project in brief: Active Construction: Foundation work in progress: Buildings 1, 31, 32, and 67 Structural work in progress: Buildings 27, 59, 60, 63, 65, and 68 Structure completed: Buildings 2, 3, 5, 9, 10, 11, 12, 13, 18, 19, 20, 22, 23, 24, 25, 26, 28, 29, 30, 33, 34, 39, 36, 37, [...]
November 30, 2020
Project in brief: Activeconstruction: Foundation work: Buildings 1, 30, 31, 32, 67. Structural work: Buildings 22, 23, 27, 59, 60, 63, 65, 68. Structure completed: Buildings 2, 3, 5, 9, 10, 11, 12, 13, 18, 19, 20, 24, 25, 26, 28, 29, 33, 34, 39, 36, 37, 38, 40, 41, 42, 44, 45, 50, 51, [...]
October 28, 2020

Project in Brief Active Construction Foundation work and structural work continue with various structures now complete. Main Structure Completed During this month, we have finished the main structure of various buildings. For these buildings, the main structure, including the foundations and bracing beams to the roof floor, are now complete. After completion of the main […]

September 15, 2020

Project in Brief Active Construction Foundation work: We are currently laying the foundations for various buildings. Structural work: For most buildings, structural work is ongoing. Structure completed: Several buildings now have a completed structure. CONSTRUCTION PROGRESS BY BUILDING THE FOUNDATION WORK We began the construction of new buildings a month ago and these buildings are […]

August 10, 2020

Project in Brief Buildings under construction: There are various buildings under construction, several of which have ongoing structural work, including additional tie beams (bracing beams). The super structure for some buildings is now complete and, for these, wall installation is underway. One building is on hold because it poses an obstruction to other buildings and […]

July 9, 2020

Project in Brief Buildings under construction: There are now many buildings under construction, several of which are undergoing structural work, including additional tie beams (bracing beams). The super structure for some is now complete and wall installation has begun. One building is awaiting further work due to the obstruction to other structures and two buildings […]

April 2, 2020

PROJECT IN BRIEF – Under construction:  There are many buildings under construction, some of which have ongoing structural work. At the current time, additional tie beams (bracing beams) are being worked on for these buildings. The super structure is now complete for several buildings and wall installation has begun. One building is currently awaiting the […]

March 4, 2020

PROJECT IN BRIEF – Under construction and complete: There are now many new buildings under construction and many for which foundations are complete. Now, we are working on the tie beams for these. – The wall work: Several buildings now have a completed superstructure and wall installation has now begun for them. – The project […]

January 30, 2020

PROJECT IN BRIEF – Foundation work done: Several buildings now have completed foundations and tie beam work continues. – The upper area: A lot of rock was encountered in the upper zone area, which obstructed the construction of the buildings. The contractors have now cleared this hard rock and are now all set to complete […]

SHOPPING CART
en_USEnglish
ru_RURussian en_USEnglish