Project in Brief

  • Active Construction
  • Foundation work: We are currently laying the foundations for various buildings.
  • Structural work: For most buildings, structural work is ongoing.
  • Structure completed: Several buildings now have a completed structure.

CONSTRUCTION PROGRESS BY BUILDING

THE FOUNDATION WORK

We began the construction of new buildings a month ago and these buildings are currently in the foundation stage. Starting with soil excavation, we worked on achieving the right ground level, then, once we reached the desired level, we packed in sand and worked on the concrete for the building foundations.

Foundation Work in Progress

Foundation Work in Stages

More Foundation Work

Foundations, from Excavation to Footings

Excavation and Footings

STRUCTURAL WORK

The 2nd floor slab for the building below is complete. We continued with the 3rd floor support column.

(Above) The shuttle board was installed to support the 2nd floor slab.

The MEP sleeve was installed before pouring the concrete for the 2nd floor slab.

(Above) The concrete slab floor has dried, so we install the column to support the floor on the next level.

Staircase in Progress

Work on the staircase for this pair of buildings is in progress and set to be completed soon.

Building Requiring Rock Clearance

Progress for the building below was delayed due to the need to first deal with the hard rock found in the area. After clearing the rock out, we have made good progress. We are currently at the halfway stage with the 2nd floor slab complete. Next, we continued with the column work on the 2nd floor to support the 3rd floor slab.

(Left) The whole building when work began on the columns.

(Right) The 2nd floor column being installed to support the 3rd floor.

Additional Progress

The 2nd floor slab for the building below is now complete. We are continuing with work on the columns to support the 3rd floor slab.

(Left) Work on the columns that will support the floor slab began last month.

(Right) The reinforced steel and MEP installation for the 2nd floor slab.

(Left) The concrete has been poured for the 2nd floor slab. (Right) The latest photo of the whole building.

Construction Nearing Completion

The structure below is almost finished with the 4th floor slab complete. This building is in the process of finishing the roof floor. This schedule for the completion of this building is just weeks away.

(Above) The columns and the scaffold are installed to support the roof floor.

(Above) The plywood formwork is installed with reinforced steel and an MEP conduit.

Additional Structures Nearing Completion

The schedule for the completion of this building’s structure is just weeks away. Currently, we are working on the roof floor of the building.

(Above, left) The building with the 4th floor slab. (Right) Installation of the shuttle board formwork for the roof floor.

(Above, left) Workers soak the area to prepare for the concrete pouring. (Right) A photo of the whole building.

Staircase

With the main structure complete, work continues with the staircase.

Additional Floor Installation

With 1st floor slab columns completed and ready to support the 2nd floor, installation of the next floor continues.

(Above, left) The 1st floor slab is complete. (Right) Column work installation follows.

(Above) The scaffold is installed to support the formwork for the 2nd floor slab.

Additional Column Installation

For the building below, the 1st floor slab is complete. Our workers continue with the installation of reinforced steel for the new columns.

(Above, left) Workers pouring concrete into the 1st floor support columns.

(Right) The scaffold is installed to support the 1st floor.

(Above) Workers install the reinforced steel bars and the post-tension sling prior to concrete pouring.

(Above, right) the 1st floor slab is dry and ready for new column installation.

Additional Floor Installation

For the building below, the 2nd floor slab and the columns above it are complete, and work continues on the 3rd floor slab.

(Above) Installation of column work on the 2nd floor. (Right) Workers have installed the reinforced steel bars and the post-tension sling and prepare to pour the concrete for the 3rd floor.

First Floor Installation

With the bracing beams complete, work continues in the 1st floor slab.

(Above) Column work on the 2nd level bracing beams.

(Above) Installation of the scaffold and formwork to support the concrete pouring for the 1st floor slab.

PLASTERING AND PAINTING WORK

We continued with the plastering and painting work of the buildings for which the walls are complete.

Plastering and Painting of Completed Buildings

(Above) A view of the building from the exterior and workers plastering the internal walls.

(Left and right) Workers plastering the external walls on the scaffold.

(Left and center) Workers install the scaffold outside the building and work on the external plastering.

(Right) The wall of the building with completed skim coat plastering.

Workers add a skim coat of plaster on the internal walls.

Completed Building

100% of the structure of this building is complete. During this month, we worked on the columns for the 2nd floor slab, then the roof floor will be ready for the concrete to be poured.

(Above) The columns are installed on the top of the 2nd floor slab. Workers transfer the column formwork from the ground to the building by tower crane.

(Above) Once the column work is complete, we install the scaffold and the shutter board formwork on the top, ready for the roof floor installation.