Project in brief:
Active Construction:
- Foundation work in progress: Buildings 1, 31, 32, and 67
- Structural work in progress: Buildings 27, 59, 60, 63, 65, and 68
- Structure completed: Buildings 2, 3, 5, 9, 10, 11, 12, 13, 18, 19, 20, 22, 23, 24, 25, 26, 28, 29, 30, 33, 34, 39, 36, 37, 38, 40, 41, 42, 44, 45, 50, 51, 52, 53, 54, 55, 57, 61, and 62.
FOUNDATION WORK
The foundation work for some buildings has been progressing this month. Further details are shown below.
Excavation in the Construction Area and Some of the Reinforced Steel Bars being Prepared Onsite
Building Materials being Prepared at the Workstation
Working on Footings; Concrete is Used for the Base of the New Footings
The Formwork is Installed, and the Reinforced Steel Bars are Installed Inside the Formwork
- Concrete is Poured into the Formwork to Make the Footings for the Buildings
- STRUCTURAL WORK
The footings for some buildings, for which the foundation work was started last month, is now complete and structural work is now in progress. We started with the column work and the bracing beams, which make up the structure that will support the whole building.
- The Footings are Complete and Ready for the Column Work
Once the Column Work is Complete, the Formwork for the Bracing Beams is Installed
- The Formwork is Complete and Ready for the Concrete Pouring
The Concrete is Poured into the Formwork for the Bracing Beams
OTHER STRUCTURAL WORK
Additional structural work is ongoing. For most of these buildings, the column work and floor structures are currently being worked on.
Workers Install Shutter Boards for the Floor Work
Workers Install Reinforced Steel Bars for the Floor Work, and then, the MEP Work is Installed Before the Concrete is Poured
Concrete is Poured for the Floor and the Columns of Other Buildings
GLASS PANEL INSTALLATION
We began installing glass panels for the guest rooms last month. This month, the work continued until the glass panels for both buildings were complete.
(Left) A Worker Cuts into the Floor to Create an Indentation for the Curtain Level
(Middle) The Frame is Installed
(Right) The Glass Panels are Fitted
A Picture Shows the Completion of the Glass Panel Installation in a Guest Room
A Picture Showing the Completion of the Glass Panel Installation for the Buildings from the Exterior
A NEW TOWER CRANE
An additional tower crane was required for the project since the 3 cranes that we have are insufficient for the efficient transfer of material.
The New Tower Crane is Delivered to the Site Ready for Installation
The Crane is Set in Place Onsite
PAINTWORK
The painting of the guest rooms is now completed, and we are continuing to paint other interior areas, such as the hallways, staircases, and ceilings.
A Worker Plasters the Exterior of the Building
Workers Plaster and Paint the Hallway and Staircase
Workers Install a Scaffold to Reach High Areas on the Staircase and Ceiling