Project in brief:

Active Construction:


  • Foundation work in progress: Buildings 1, 31, 32, and 67
  • Structural work in progress: Buildings 27, 59, 60, 63, 65, and 68
  • Structure completed: Buildings 2, 3, 5, 9, 10, 11, 12, 13, 18, 19, 20, 22, 23, 24, 25, 26, 28, 29, 30, 33, 34, 39, 36, 37, 38, 40, 41, 42, 44, 45, 50, 51, 52, 53, 54, 55, 57, 61, and 62.

FOUNDATION WORK
The foundation work for some buildings has been progressing this month. Further details are shown below.


 

Excavation in the Construction Area and Some of the Reinforced Steel Bars being Prepared Onsite


 

Building Materials being Prepared at the Workstation


 

Working on Footings; Concrete is Used for the Base of the New Footings


 

The Formwork is Installed, and the Reinforced Steel Bars are Installed Inside the Formwork



 

 

  •  
  • The Footings are Complete and Ready for the Column Work


 

Once the Column Work is Complete, the Formwork for the Bracing Beams is Installed


 

The Concrete is Poured into the Formwork for the Bracing Beams

 

 

OTHER STRUCTURAL WORK

Additional structural work is ongoing. For most of these buildings, the column work and floor structures are currently being worked on.


Workers Install Shutter Boards for the Floor Work

 

  •       

 

Workers Install Reinforced Steel Bars for the Floor Work, and then, the MEP Work is Installed Before the Concrete is Poured

  •       

 

Concrete is Poured for the Floor and the Columns of Other Buildings

 

 

GLASS PANEL INSTALLATION

We began installing glass panels for the guest rooms last month. This month, the work continued until the glass panels for both buildings were complete.


 

(Left) A Worker Cuts into the Floor to Create an Indentation for the Curtain Level

(Middle) The Frame is Installed

(Right) The Glass Panels are Fitted

  •       

 

A Picture Shows the Completion of the Glass Panel Installation in a Guest Room

  •       

 

A Picture Showing the Completion of the Glass Panel Installation for the Buildings from the Exterior

 

 

A NEW TOWER CRANE

An additional tower crane was required for the project since the 3 cranes that we have are insufficient for the efficient transfer of material.

  •       

 

The New Tower Crane is Delivered to the Site Ready for Installation

  •       

 

The Crane is Set in Place Onsite

 

 

PAINTWORK

The painting of the guest rooms is now completed, and we are continuing to paint other interior areas, such as the hallways, staircases, and ceilings.


 

A Worker Plasters the Exterior of the Building


 

Workers Plaster and Paint the Hallway and Staircase


 

Workers Install a Scaffold to Reach High Areas on the Staircase and Ceiling

 