Project in Brief:

 

Active Construction:

  • Foundation work in progress for several buildings.
  • Structural work in progress for various buildings.
  • Structure completed for most buildings.
  • Wall panels are completed for various buildings.
00_02
00_03

(Above) An Overview of the Construction Area

FOUNDATION WORK

This month we focused on the foundation for few buildings in the upper zone, which is the tricky part compared to the rest of the project.  In this area, several rocks need to be removed before we can safely start the foundation. After the rocks that are in the way have been demolished, we start our foundation work by attaching them to existing rocks that were left in the area. This is the longest part of the project; we have to demolish all the obstructing rocks for the next couple of months until we get the perfect level to start with our building foundation.

01_01
01_02

The workers installed the formwork next to the rock.

01_03
01_04

Concrete pouring into the formwork.

01_05
01_06
01_07

WALL WORK

Over the last few months, our team completed most of the structural work for Grand Himalai. At the moment we are in the Wall building/installation phase, where we have been using the Q-con wall panel to help save time and money, and we plan to hire more manpower next month to assist with this phase.

02_00_wall01
02_00_wall02

(Above) Materials for the wall now onsite.

02_00_wall03
02_00_wall04

(Above) The installation team installing the wall panels.

02_00_wall05
02_00_wall06

(Above) This room’s walls have been successfully installed. (right) A look from the outside at our completed wall installation on this building.

STRUCTURAL WORK

There is very little structural work left because we are mostly finished with that phase. However, in the following months, we will continue to complete the buildings by installing bracing beams and floor slabs.

02_01-please crop
02_02

(Above) Bracing beam work continues on the Building; in these pictures, the workers are going to install the reinforced steel for the bracing beam and its column work.

02_03-please crop
02_04

(Above) Another building undergoing bracing beam work (Right) Another building gets the scaffolding installed to help support its floor slab.

02_05-please crop
02_06-please crop

(Above) The workers are installing the scaffolding for its floor slab.

02_07-please crop
02_08

(Above) The shutter boards will be installed on the top of the scaffolding.

02_09-please crop
02_10

(Above) The engineer has an inspection of the area in which the shutter boards are being installed. (Right) another building is ready for its concrete flooring.

PREPARATION OF THE CONSTRUCTION AREA FOR NEW BUILDINGS

The front of the project has been turned into a workstation for material preparation.

03_01
03_02

(Above) The materials being delivered to the work station in the front of the project. (Right) Preparing the materials before transferring them up to the construction area.

03_03
03_04

(Above) The workers preparing the steelwork for the structure of the buildings.

03_05
03_06

(Above) The worker preparing the steelwork for the structure of the buildings.

03_07
03_08

(Above) The worker preparing the steelwork for the structure of the buildings.

SHOPPING CART
en_USEnglish
ru_RURussian en_USEnglish