Project in Brief:
Active Construction:
- Foundation work in progress for several buildings.
- Structural work in progress for various buildings.
- Structure completed for most buildings.
- Wall panels completed for various buildings.
FOUNDATION WORK
The structural work is now complete for the vast majority of the project. This month, we continued working on the structure of a few buildings that require ongoing structural work. Most of the work that we have carried out during this month has involved preparing material, clearing the construction area, and surveying the area for new buildings.




(Above) An Overview of the Construction Area
There are a few buildings in the middle zone and one in the upper zone that are currently undergoing foundation work (the buildings shown in red on the diagram above). We are working on the footing work for these buildings, and the micro piling for the foundation of one building in the upper zone is now complete.





(Above) Images Show the Progress of the Footing Work for the Buildings in the Middle Zone



(Above) Workers Prepare Reinforced Steel Bars for the Footing of the Buildings


(Above) Work Continues on the Bracing Beams After Footings are Complete
(Right) Shutter Board Formwork Installation for the 1st Level of Bracing Beams
STRUCTURAL WORK
Structural work is ongoing for several buildings. This includes column work and bracing beams.

(Above) Column Work Continues on the Building Above Once the Footing is Complete


(Note: Please crop these pictures)
(Above) Bracing beams are placed on the top of the columns.

(Above) Once the Columns are Completely Dry, the Scaffold is Installed to Support the Next Level of Bracing Beams


(Above) Preparation for Column Installation on the Bracing Beams and Scaffold Installation to Provide Support for the Next Level of Bracing Beams


(Above) The 1st Level Bracing Beams for this Building are Complete and Workers Install Reinforced Steel Bars for the Column Work
(Right) Materials are Transferred Onsite via the Tower Crane

(Above) A Building Awaits Formwork Installation for Columns


(Above) Floor Work Continues for Some Buildings, for Which the Structural Work Will Soon be Complete
NEW TOWER CRANE
An additional tower crane was brought onto the site at the end of December to optimize construction.


(Above) The New Tower Crane is Transferred to the Site and Assembled on Location


(Above) The Crane being Set in Place Onsite

(Above) Concrete is Poured into the Tower Crane Base to Stabilize It
PREPARATION OF THE CONSTRUCTION AREA FOR NEW BUILDINGS
Certain areas, mostly located on roadways or access points, are being prepared for construction. This month, we are in the process of surveying these areas, with construction for the footings set to begin in due course.


(Above) The Surveying Team Inspects the Construction Area for the New Buildings


(Above) The Materials are Delivered to the Workstation in Front of the Project





(Above) Workers Prepare the Materials for the New Buildings While the Construction Area is Being Surveyed