Project in Brief:

 

Active Construction:

  • Foundation work in progress.
  • Structural work in progress for various buildings.
  • Structure completed for most buildings.
  • We completed wall panels for various buildings.

Because of the decrease in infections in Phuket, Covid-19 restrictions are being lifted, meaning workplaces, schools, and restaurants are now open again. However, there are still restrictions in place from the provincial government that limit the number of workers allowed on-site to not over 30 people. Because of this, we have limited human resources and the structural work took longer than first planned. We are still seeing good progress in the middle zone primary structures, the lift structures, and the internal wall work.

STRUCTURAL WORK

The Lift Work

We have continued the lift structure work next to the building that we have completed structurally. Right now the progress is 1 level a week. This is because the number of workers has to be reduced on-site to adhere to the restriction order.

00_01
00_02
00_03

The worker tied the steel bars to reinforce the lift structure.

The Main Structure

This month we are working on the structure of the building in the mid-zone. At the beginning of this month, we finished the last level of the bracing beam and continued with the first-floor slab for the building.

02_01
02_02

The concrete pouring for the last level of the bracing beam.

02_03
02_04

The first-floor slab work has started. The scaffolding is already installed and the shutter boards formwork are being installed above it.

02_05
02_06

(Left) The engineer inspected the board installation. (Right) The workers tied the steel together for the building’s column.

02_07
02_08

We tied the reinforced steel bars all over the area of the floor slab.

02_09
02_10

The concrete pouring after all the reinforced steel bars and the post-tension slings have been installed.

WALL WORK

We have started the plastering work on the wall panels to finish the installation. We have plastered it from inside the building outwards.

03_001
03_000

The internal wall panels installed on site.

03_01
03_02

(Left) This area is ready for plastering.

03_03
03_04

(Right) The worker started the skim coat the wall.

03_05
03_06

The walls have to be brushed and polished to make the walls smooth.

Material Preparation

We are currently preparing the material for the upper zone of the site, which we will continue once the restrictions are over. We are preparing the materials at the workstation and will transfer them to the cranes once the time is right.

04_01
04_02

The workers prepare the material for the building structure.

04_03
04_04

The materials are being transferred to the storage location in the upper zone.