Project in brief:

Active
construction:

  • Foundation work: Buildings 1, 30, 31, 32, 67.
  • Structural work: Buildings 22, 23, 27, 59, 60, 63, 65, 68.
  • Structure completed: Buildings 2, 3, 5, 9, 10, 11, 12, 13, 18, 19, 20, 24, 25, 26, 28, 29, 33, 34, 39, 36, 37, 38, 40, 41, 42, 44, 45, 50, 51, 52, 53, 54, 55, 57, 61, 62.

 

Building structure completed
This month the building 22 has just finished the structure work. This building has 4 story and 2 levels of bracing beam.

 

(left) the building 22 stand next to building 23 at the front view. (right) the building at the back view.

 

The building when it was working on the slab concrete for the roof floor.

 

THE FOUNDATION WORK
Construction has begun on an additional 5 buildings. This month, we have been working on the foundations for these new buildings. The foundation work includes the footings and the column work for the first level of bracing beams.


Surveying the mid-zone buildings.


In the target area, after we have performed a survey, we mark the boundary for the new building area. Next, we excavate the area to prepare it for the footing.


The workers prepare the materials for the new building structure.


The material is transferred from the lower zone workstation to the building area.



The footing work in progress. This starts with the concrete for the base of the footing. Then, the formwork is prepared, and reinforced steel bars are placed into the formwork. Finally, the concrete is poured into the formwork.


When the footing is completely dry, the concrete is poured for the columns.

THE STRUCTURAL WORK



The structural work continues after the footings are complete. Work progresses on the 1st level bracing beams, for which the formwork is complete and awaits the pouring of the concrete.


Floor work in progress. The engineer inspects the reinforced steel and post-tension sling in the shutter board formwork.

STAIR WORK

Stair work progresses for the building below, for which the main structure is complete.


The reinforced steel bars are installed in the formwork. This will add strength and increase the loading factor of the stair structure.


The stair work after the concrete has been poured.

ELEVATOR WORK

The elevator of the building below is being constructed on the exterior, adjacent to the building.


ARCHITECTURAL
WORK

PLASTERING AND PAINTING


The scaffold is installed outside the building for plastering and painting the exterior.


Workers plaster the interior walls.


The interior painting work in progress.


Workers on the scaffold paint the exterior wall.

GLASS PANEL INSTALLATION

The main structure and walls of 2 buildings are now complete. While we are working on the wall plastering and painting, we have started to install the glass panels of the building.


A worker levels the floor, and then makes a curb for the base of the glass sliding doors.


The frame is installed over the floor curb.


The installation is complete.


The sliding glass door installation from the exterior.


 